On Site | Update Konrad-Zuse-Schule
The building of the workshop is now entering the next stage. In only 6 weeks the buildings structure has been assembled, including the roof elements that were installed last week, and as we speak the prefabricated outer are being delivered and mounted.
Because the outer walls are not load-bearing they are prefabricated and delivered on site to be directly mounted on toe the skeleton structure. The firm Sieveke builds the outer walls in their factory and they are completed with insulation and windows. Only missing is the cladding which will be added to the building once the walls are all mounted.
https://vimeo.com/434348586