On site | Konrad-Zuse-Schule
The new workshop building for the Konrad-Zuse-Schule is currently being built. In only 5 weeks the complete structure, consisting of columns and beams, inner walls in load-bearing CLT, ceiling elements and the roof has gone up. The highly prefabricated elements, which is possible in modern timber construction, makes it possible to assemble the building fast and precise. Because the construction site low-noise, clean and mostly dust-free the school can operate as normal during the time the new building is being constructed.
Photographer: Matthew Crabbe